Relocation and equipment install from Mount Waverley Victoria to Rooty Hill NSW (March 2017 > August 2018)
Scope: Relocation of General Mills Victoria to Rooty Hill NSW
Jarlam provided complete project management for this relocation.
Relocation of 4 production lines from Mount Waverley Vic to Rooty Hill NSW. We achieved tight deadlines by running 24hr labour coverage (10 days to remove & reinstall the lines)
Install stainless steel chilled water lines throughout plant